Project Management Professional (PMP) Exam Practice – Question1428
The cumulative CPI has been shown to be relatively stable after what percentage of project completion?
A. 5% to 10% B. 15% to 20% C. 25% to 35% D. 50% to 75%
Correct Answer: B
Explanation:
Explanation:
The CPI has been proven to be an accurate and reliable forecasting tool. Researchers have found that the cumulative CPI does not change by more than 10% once a project is approximately 20% complete. The CPI provides a quick statistical forecast of final
project costs.