Project Management Professional (PMP) Exam Practice – Question1429

The undistributed budget is part of the______________


A.
Management reserve
B. Performance measurement baseline
C. Level-of-effort cost accounts
D. General and administrative accounts

Correct Answer: B

Explanation:

Explanation:
The undistributed budget is applied to project work that has not yet been linked to WBS elements at or below the lowest level of reporting. It is, therefore, part of the performance measurement baseline and is expected to be used in the performance of project
work.