Project Management Professional (PMP) Exam Practice – Question1432

There are a number of different earned value management rules of performance measurement that can be established as part of the cost management plan. Which one of the following is NOT an example of such a rule?


A.
Code of accounts allocation provision
B. Formulas to determine the ETC
C. Earned value credit criteria
D. Definition of the WBS level

Correct Answer: A

Explanation:

Explanation:
Rules of earned value performance measurement are part of the cost management plan and may (1) define the points in the WBS where measurement of control accounts will be performed; (2) establish the EV measurement techniques such as weighted
milestones, fixed-formula, percent complete, etc., to be used; and (3) specific tracking methods and EV equations for calculating the EAC forecasts to provide a validity check on the bottom-up EAC.