Project Management Professional (PMP) Exam Practice – Question1435
By reviewing cumulative cost curves, the project manager can monitor______________
A. EV B. PV C. CVs D. CPI
Correct Answer: C
Explanation:
Explanation:
Cumulative cost curves, or S-curves, enable the project manager to monitor cost variances at a glance. The difference in height between the planned-expenditure curve and the actual-expenditure curve represents the monetary value of variances at any given
time.