Project Management Professional (PMP) Exam Practice – Question1436

Control accounts______________


A.
Are charge accounts for personnel time management
B. Summarize project costs at level 2 of the WBS
C. Identify and track management reserves
D. Represent the basic level at which project performance is measured and reported

Correct Answer: D

Explanation:

Explanation:
Control accounts represent a management control point where scope, budget (resource plans), actual costs, and schedule are integrated and compared to earned value for performance measurement.