As project manager, you identified a number of acceptable tolerances as part of your earned value management system. During execution, some "unacceptable" variances occurred. After each "unacceptable" variance occurred, you did which one of the following
first?
A. Updated the budget
B. Prepared a revised cost estimate
C. Adjusted the project plan
D. Documented lessons learned