Assume that the project cost estimates have been prepared for each activity and the basis of these estimates has been determined. Now, as the project manager for your nutrition awareness program in your hospital, you are preparing your budget. Because you
have estimates for more than 1,200 separate activities, you have decided to first______________
A. Aggregate these estimates by work packages
B. Aggregate these estimates by control accounts to facilitate the use of earned value management
C. Use the results of previous projects to predict total costs
D. Set your cost performance baseline
have estimates for more than 1,200 separate activities, you have decided to first______________
A. Aggregate these estimates by work packages
B. Aggregate these estimates by control accounts to facilitate the use of earned value management
C. Use the results of previous projects to predict total costs
D. Set your cost performance baseline