Project Management Professional (PMP) Exam Practice – Question1445

The cumulative cost curve for planned and actual expenditures______________


A.
Helps to monitor project performance at a glance
B. Is used for calculating the CPI
C. Is also known as a histogram
D. Forecasts total project expenditures

Correct Answer: A

Explanation:

Explanation:
Cost curves for planned and actual expenditures are created by adding each month’s costs to the previous reporting period’s expenditures. By doing so, one can quickly see how the project is performing.