The reason that the cost performance index (CPI) is shown as a ratio is to______________
A. Enable a detailed analysis of the schedule regardless of the value of the schedule variance
B. Distinguish between critical path and noncritical path work packages
C. Provide the ability to show performance for a specified time period for trend analysis
D. Measure the actual time to complete the project