Project Management Professional (PMP) Exam Practice – Question1451

In quality management, the practice "rework" is______________


A.
Acceptable under certain circumstances
B. An adjustment made that is based on quality control measurements
C. Action taken to bring a defective or nonconforming component into compliance
D. Not a concern if errors are detected early

Correct Answer: C

Explanation:

Explanation:
Rework is a frequent cause of project overruns. The project team must make every reasonable effort to control and minimize rework so that defective or nonconforming components are brought into compliance with requirements or specifications.