In quality management, the practice "rework" is______________
A. Acceptable under certain circumstances
B. An adjustment made that is based on quality control measurements
C. Action taken to bring a defective or nonconforming component into compliance
D. Not a concern if errors are detected early
A. Acceptable under certain circumstances
B. An adjustment made that is based on quality control measurements
C. Action taken to bring a defective or nonconforming component into compliance
D. Not a concern if errors are detected early