When a process is within acceptable limits, it______________


A.
Should not be adjusted
B. May not be changed to provide improvements
C. Shows differences caused by expected events or normal causes
D. Should not be inspected or reworked for any reason

Correct Answer: A

Explanation:

Explanation:
Processes should be changed only through established change procedures. If the process is outside acceptable limits, it should be adjusted.