The project team should have a working knowledge of statistical process control to help evaluate control quality outputs. Of all the topics involved, which of the following is the most important for the team to understand?
A. Sampling and probability
B. Attribute sampling and variables sampling
C. Tolerances and control limits
D. Special causes and random causes
A. Sampling and probability
B. Attribute sampling and variables sampling
C. Tolerances and control limits
D. Special causes and random causes