Project Management Professional (PMP) Exam Practice – Question1460

The project team should have a working knowledge of statistical process control to help evaluate control quality outputs. Of all the topics involved, which of the following is the most important for the team to understand?


A.
Sampling and probability
B. Attribute sampling and variables sampling
C. Tolerances and control limits
D. Special causes and random causes

Correct Answer: A

Explanation:

Explanation:
Sampling and probability form the basis of statistical process control, which helps the team monitor project results for compliance with relevant quality standards so that methods can be identified to eliminate causes of unsatisfactory results.