Your quality assurance department recently performed a quality audit of your project and identified a number of findings and recommendations. One recommendation seems critical and should be implemented because it affects successful delivery of the product
to your customer.
to your customer.
Your next step should be to______________
A. Call a meeting of your project team to see who is responsible for the problem
B. Reassign the team member who had responsibility for oversight of the problem
C. Perform product rework immediately
D. Issue a change request to implement the needed corrective action