You recognize the importance of quality control on your project. However, you also know that quality control has costs associated with it and that the project has a limited budget. One way to reduce the cost of quality control is to______________
A. Work to ensure that the overall quality program is ISO compliant
B. Use statistical sampling
C. Conduct inspections throughout the process
D. Use trend analysis