Project Management Professional (PMP) Exam Practice – Question1475

Results of quality control measurements are used______________


A.
As an input to plan quality management
B. To prepare an operational definition
C. To prepare a control chart
D. As an input to perform quality assurance

Correct Answer: D

Explanation:

Explanation:
Quality control activities result in measurements that are used as inputs to the QA process. Such quality control measurements are used to evaluate and analyze the quality of the processes of the project against the organization’s standards or specific
requirements. They also compare processes used to create the measurements and validate actual measurements to determine their level of correctness.