The control chart is a tool used primarily to help______________


A.
Monitor process variation over time
B. Measure the degree of conformance
C. Determine whether results conform
D. Determine whether results conform to requirements

Correct Answer: A

Explanation:

Explanation:
Used to monitor process variation and to detect and correct changes in process performance, the control chart helps people understand and control their processes and work. It enables the project manager, along with appropriate stakeholders, to identify points
where corrective action can be taken to prevent unnatural performance.