Project Management Professional (PMP) Exam Practice – Question1481

All of the following are objectives of a quality audit except______________


A.
Defect repairs have been implemented
B. Improvement opportunities are identified
C. Good practices can be introduced elsewhere
D. Root cause analysis has been performed as part of process analysis

Correct Answer: D

Explanation:

Explanation:
The purpose of the quality audit is to determine if project activities comply with organizational policies, procedures, and processes. The quality audit has a number of objectives associated with it, but root cause analysis is part of process analysis to identify needed
improvements in the process improvement plan.