Constancy of purpose is a core concept for continuous improvement. An organization displaying constancy of purpose must have all the following elements EXCEPT______________


A.
Documented and well-disseminated statements of purpose and vision
B. A set of strategic and tactical plans
C. An awareness by all members of the organization of the purpose, vision, goals, and objectives and their roles in achieving them
D. Separate quality assurance and quality control departments reporting to senior management

Correct Answer: D

Explanation:

Explanation:
Top management should provide constancy of purpose so that it can be infused throughout the organization. Constancy of purpose also requires a shared belief among organization members that management’s behavior clearly signals its commitment to and
support of achievement of the vision. Quality assurance and control are functions that must be performed by everyone, not just those assigned to specific departments.