Project Management Professional (PMP) Exam Practice – Question1484

Quality objectives of the project are recorded in______________


A.
Process improvement plan
B. Quality management plan
C. Quality baseline
D. Quality metrics

Correct Answer: B

Explanation:

Explanation:
The quality management plan describes how the team will implement the quality policy, which describes the objectives of the project regarding quality management.