Project Management Professional (PMP) Exam Practice – Question1488

The quality management plan describes all the following EXCEPT the______________


A.
Method for implementing the quality policy
B. Methods the team will use to meet the project's quality requirements
C. Efforts at the front end of a project to ensure that decisions are based on accurate information
D. Procedures used to conduct trade-off analyses among cost, schedule, and quality

Correct Answer: D

Explanation:

Explanation:
A part of the overall project management plan, the quality management plan should address all aspects of how quality management will be implemented on the project and how the project team will implement the quality policy. Trade-off analyses are business
judgments and, as such, are not procedural steps to be included in the quality management plan.