Project Management Professional (PMP) Exam Practice – Question1489

You have been assigned as project manager on what could be a "bet the company" project. You realize that to be successful you need to exercise maximum control over project resources. Which form of project organization should you establish for this project?


A.
Strong matrix
B. Projectized
C. Project coordinator
D. Weak matrix

Correct Answer: B

Explanation:

Explanation:
In a projectized organizational structure, all project team members report directly and solely to the project manager. He or she has complete control over these resources and, therefore, exercises more authority over them than when in any other project
organizational structure.