Project Management Professional (PMP) Exam Practice – Question1491

Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the
project manager?


A.
The project manager will probably not be challenged by project stakeholders.
B. In this strong matrix, the balance of power is shifted to the functional line managers.
C. In this tight matrix, the balance of power is shifted to the project manager.
D. In this strong matrix, the balance of power is shifted to the project manager.

Correct Answer: D

Explanation:

Explanation:
The project manager’s ability to influence project decisions increases the higher up he or she______________and the person to whom he or she reports______________is placed in the organization. In the strong matrix, the project manager’s authority ranges
from moderate to high.