Project Management Professional (PMP) Exam Practice – Question1498

As you prepare your human resource plan, you need to determine the skill and capacity required to complete the activities in the project. This should be documented in the______________


A.
Roles and responsibilities section
B. Staffing management plan
C. Staff acquisition section
D. Compliance section

Correct Answer: A

Explanation:

Explanation:
Roles and responsibilities are listed in the human resource plan. This section describes roles and authority, responsibility, and competency or the skill and capacity required to complete project activities. When team members do not have the required
competencies, project performance may be jeopardized and the project manager must have proactive responses to handle these situations.