Project Management Professional (PMP) Exam Practice – Question1500

The team members on your project have been complaining that they do not have any sense of identity as a team because they are located in different areas of the building. To remedy this situation, you developed a project logo and had it printed on T-shirts to
promote the project, but this action has not worked. Your next step is to______________


A.
Initiate a newsletter
B. Create an air of mystery about the project
C. Establish a "team meeting room"
D. Issue guidelines on how team members should interact with other stakeholders

Correct Answer: C

Explanation:

Explanation:
Collocating team members, even on a temporary basis, enhances communications, thereby contributing to improved project performance. In addition, the “team meeting room” (often called a `war room’) provides a sense of identity to the project team and raises
the visibility of the project within the organization. Creating a newsletter is simply applying another organizational process asset, which typically has proven ineffective.