Project Management Professional (PMP) Exam Practice – Question1501

The project team directory is an output from which of the following processes?


A.
Develop project team
B. Acquire project team
C. Develop human resource management plan
D. Manage project team

Correct Answer: B

Explanation:

Explanation:
The project team directory is part of project staff assignments, an output from the acquire project team process. Other outputs are resource calendars and updates to the project management plan.