Project Management Professional (PMP) Exam Practice – Question1507

As project manager, you are primarily responsible for implementing the project management plan by authorizing the execution of project activities. Because you do not work in a projectized organization, you do not have direct access to human resource
administrative activities.

Therefore you need to______________


A.
Outsource these functions
B. Prepare a project team charter that is signed off by a member of the human resources department to delineate responsibilities
C. Ensure that your team is sufficiently aware of administrative requirements to ensure compliance
D. Ask the head of human resources to approve your project human resource plan personally

Correct Answer: C

Explanation:

Explanation:
A projectized work environment is unusual because project managers rarely have every function under their control. But compliance with administrative requirements, government regulations, union contract provisions, and other constraints is a consideration in
human resource management.