Your project has been under way for some time, but indicators show that it is in trouble. You have observed all the following symptoms of poor teamwork in your project team EXCEPT______________


A.
Frustration
B. Excessive meetings
C. Lack of trust or confidence in the project manager
D. Unproductive meetings

Correct Answer: B

Explanation:

Explanation:
The problem is not too many meetings, but unproductive ones. The purpose of project meetings is to focus the skills and resources of the project team on project performance. Meetings that are considered “gripe sessions” or a time for the project manager to “lay
down the law” are demoralizing to the team.