Project Management Professional (PMP) Exam Practice – Question1515

The major difference between the project coordinator and project expeditor forms


A.
Strong commitment to the project usually does not exist in the project expeditor form of organization
B. The project coordinator cannot personally make or enforce decisions
C. The project expeditor acts only as an intermediary between management and the project team
D. The project coordinator reports to a higher-level manager in the organization

Correct Answer: D

Explanation:

Explanation:
The relative position of the project coordinator in the organization is thought to lead to an increased level of authority and responsibility.