Project Management Professional (PMP) Exam Practice – Question1516

Which one of the following represents a constraint on the acquire project team process?


A.
Pre assignment of staff to the project
B. Recruitment practices of the organizations involved
C. Use of outsourcing
D. Team member training requirements

Correct Answer: B

Explanation:

Explanation:
Staff assignments in organizations are governed by the policies, procedures, or guidelines of individual components. These policies will constrain the project manager’s actions in acquiring a project team. The more familiar the project manager is with such
policies, the easier it will be for him/her to assemble a team. Such recruitment practices are examples of personnel administration policies; an enterprise environmental factor, which is an input to acquire project team.