Project Management Professional (PMP) Exam Practice – Question1521

The chances for successful completion of a multidisciplinary project are increased if project team members are______________


A.
Problem oriented
B. Politically sensitive to top management's needs

C. Focused on individual project activities
D. Focused on customer demands

Correct Answer: A

Explanation:

Explanation:
Problem-oriented people tend to learn and use whatever problem-solving techniques appear helpful. Although the project manager must be politically sensitive, team members need not have developed this skill to the extent required of the project manager; and
rather than focusing on individual activities, team members should take a systems approach focusing on the entire project.