Project Management Professional (PMP) Exam Practice – Question1526

Conflicts in which following three areas represent the majority of all project conflicts?


A.
Personalities, cost objectives, and schedules
B. Cost objectives, administrative procedures, and scarce resources
C. Scarce resources, scheduling priorities, and personal work styles
D. Personal work styles, project priorities, and cost objectives

Correct Answer: C

Explanation:

Explanation:
Although all areas listed contain potential conflicts, the majority of all conflict in a project environment is caused by scarce resources, scheduling priorities, and personal work styles.