Project Management Professional (PMP) Exam Practice – Question1528

Determining the method and the timing of releasing team members should be included in the______________


A.
Staff acquisition plan
B. Human resource plan
C. Staffing management plan
D. Project training plan

Correct Answer: C

Explanation:

Explanation:
The staffing management plan is a document that describes when and how human resources will become part of the project team and when they will return to their organizational units. It addresses how staff members will be acquired, how long they will remain on
the project, how and when they will be released, training needs, and other important aspects of forming and disbanding the team.