As project manager, you plan to conduct a "kickoff" meeting at which you will discuss all the following EXCEPT______________


A.
Establishing working relationships and standard formats for global communication
B. Reviewing project plans
C. Establishing individual and group responsibilities and accountabilities
D. Discussing specific legal issues regarding the contract

Correct Answer: D

Explanation:

Explanation:
Conducted after contract award or approval of the project, the kickoff meeting provides an opportunity for project participants to get to know each other and review information about the project. It is not a forum to discuss detailed project issues.