Project managers for international projects should recognize key issues in cross-cultural settings and place special emphasis on______________


A.
Establishing a performance reporting system
B. Using good communication planning
C. Establishing and following a production schedule for information distribution to avoid responding to requests for information between scheduled communications
D. Using translation services for formal, written project reports

Correct Answer: B

Explanation:

Explanation:
An effective way to manage cultural diversity on projects is for the project manager to get to know the team members and to use good communication planning. It is necessary to consider time zones and language barriers as well as cultural differences and to
include a glossary of common terminology in the communications management plan.