You are managing a project with team members located at customer sites on three different continents. As you plan communications with your stakeholders, you should review______________


A.
Stakeholder management plan
B. Stakeholder register
C. Communications model
D. Communications channels

Correct Answer: B

Explanation:

Explanation:
The stakeholder register is an input to the plan communications management process. It contains the identified stakeholders including their name, position, location, and role; their main requirements, expectations, and potential influence; and whether or not they
are supporters, neutral, or resistors of the project.