You are managing a project with team members located at customer sites on three different continents. As you plan communications with your stakeholders, you should review______________
A. Stakeholder management plan
B. Stakeholder register
C. Communications model
D. Communications channels
A. Stakeholder management plan
B. Stakeholder register
C. Communications model
D. Communications channels