Project Management Professional (PMP) Exam Practice – Question1538

You are responsible for a project in your organization that has multiple internal customers. Because many people in your organization are interested in this project, you realize the importance of______________


A.
Conducting a stakeholder analysis to assess information needs
B. Performing communications planning early
C. Determining the communications requirements of the customers
D. Having an expert on communications management an customer relationship management on your team

Correct Answer: B

Explanation:

Explanation:
On most projects, communications planning should be performed very early such as when the project management plan is prepared. This approach then allows appropriate resources, such as time and budget, to be allocated to communications activities.