Project Management Professional (PMP) Exam Practice – Question1542

You finally have been appointed project manager for a major company project. One of your first activities as project manager will be to create the communications management plan. As you match the stakeholder with the appropriate communication methods for
that stakeholder, you could use any one of the following methods EXCEPT______________


A.
Interactive communications
B. Passive communications
C. Pull communications
D. Push communications

Correct Answer: B

Explanation:

Explanation:
You can use several different methods to share information. Interactive communications are multidirectional in nature, such as conferences and meetings. Pull communications are those methods where the recipient finds the information at their leisure and gets
the information that they want at their discretion. Push communications is targeted information sent to a select group but does not certify that the recipient actually has received the information, such as e-mail. Passive communications is more of a style of
delivering the content or receiving the content.