As head of the PMO, you will receive performance reports for all major projects. You decided to set a guideline for project managers as performance reporting should______________
A. Collect work performance information on the status of deliverables
B. Provide earned value data for project forecasting
C. Provide information at an appropriate level for each audience
D. Focus on cost and schedule variances rather than scope, resources, quality, and risks