Project Management Professional (PMP) Exam Practice – Question1552

As an output from control communications, it may be necessary to update the______________


A.
Project schedule
B. Forecasts
C. Corporate policies, procedures, and processes
D. Knowledge management system

Correct Answer: B

Explanation:

Explanation:
Communications control often entails the need to update project documents, including forecasts, performance reports, and the issue log.