Project Management Professional (PMP) Exam Practice – Question1557

Assume on your project you have identified 250 stakeholders located in three continents and of these 250, you have determined that 200 of them will be actively involved and interested in your project. Therefore, as you determine an appropriate communication
method, your best approach is______________


A.
Elaborate status reports
B. Simple status reports
C. Knowledge repositories
D. E-mails

Correct Answer: C

Explanation:

Explanation:
Knowledge repositories along with Intranet sites, e-learning, and lessons learned data bases are examples of methods of pull communications. They are used for large volumes of information or for large audiences and require recipients to access communication
content at their own discretion.