Project Management Professional (PMP) Exam Practice – Question1558

You want to ensure that the information you collect showing project progress and status is meaningful to stakeholders. You want to combine the type and format of the stakeholder's information needs with an analysis of the value of the information. You will
document this information in the______________


A.
Communications register
B. Stakeholder register
C. Stakeholder management plan
D. Communications management plan

Correct Answer: D

Explanation:

Explanation:
The project team must conduct an analysis of stakeholder communications requirements to ensure that stakeholders are receiving the information required to participate in the project. For example, stakeholders typically require performance reports for
information purposes. Such information requirements should be included in the communications management plan.