Project Management Professional (PMP) Exam Practice – Question1559

Work performance information is an output of which process?


A.
Manage risks
B. Manage communications
C. Control communications
D. Report performance

Correct Answer: C

Explanation:

Explanation:
Work performance information, an output of control communications, organizes and summaries performance data such as status and progress information on the project at the level required by stakeholders. This information next is communicated to the
appropriate stakeholders.