Assume you want to optimize the work performance reports you will use to manage communications. You should do so by______________


A.
Determining the most appropriate choice of communications media
B. Setting different communications techniques for different stakeholder groups
C. Ensuring the information is consistent with regulations and standards
D. Ensuring comprehensiveness, accuracy, and availability

Correct Answer: D

Explanation:

Explanation:
Work performance reports are an input to manage communications. They are a collection of project performance and status information used to facilitate discussion and create communications. They should be comprehensive, accurate, and available in a timely