Project Management Professional (PMP) Exam Practice – Question1563

Changes in the report formats and lessons learned documents process should trigger changes to the______________


A.
Project management plan and performance reporting system
B. Integrated change control system and the communications management plan

C. Monitor and control project process and the project management plan
D. Organizational process assets updates

Correct Answer: D

Explanation:

Explanation:
Any changes in report formats or lessons learned documentation are organizational process asset updates as an output of control communications. The documentation may become part of the historical data base for both the project and the organization.