Project Management Professional (PMP) Exam Practice – Question1566

Because communications planning often is linked tightly with enterprise environmental factors, which one of the following statements is true?


A.
The project's organizational structure has a major effect on the project's communications requirements.
B. Standardized guidelines, work instructions, and performance measurement criteria are key items to consider.
C. Procedures for approving and issuing work authorizations should be taken into consideration.
D. Criteria and guidelines to tailor standard processes to the specific needs of the project should be stated explicitly.

Correct Answer: A

Explanation:

Explanation:
Enterprise environmental factors undoubtedly will influence the project’s success and must be considered because communication must be adapted to the project environment.