Project Management Professional (PMP) Exam Practice – Question1567
You are working on a project with 15 stakeholders. The number of communication channels on this project is______________
A. 15 B. 105
C. 210 D. 225
210 D. 225
Correct Answer: B
Explanation:
Explanation:
The formula for determining the number of communication channels is n(n -1)/2, where n = the number of stakeholders: 15(15 -1)/2 = (15)(14)/2 = 105. It is important to note that project managers must plan the project’s communications requirements carefully,
limiting who will communicate with whom given the potential for confusion when multiple communications channels can exist.