Project Management Professional (PMP) Exam Practice – Question1569

As the project manager, you have the option of proposing one of three systems to a client: a full-feature system that not only satisfies the minimum requirements but also offers numerous special functions (the "Mercedes"); a system that meets the client's
minimum requirements (the "Yugo"); and a system that satisfies the minimum requirements plus has a few extra features (the "Toyota"). The on-time records and associated profits and losses are depicted on the below decision tree. What is the expected
monetary value of the "Toyota" system?



A.
$9,900
B. $44,000
C. $45,000
D. $48,000

Correct Answer: B

Explanation:

Explanation:
EMV VToyota = ($50, 00090%) + ($10,0000%)
= $45,000+(-$1,000)
= $44,000