Project Management Professional (PMP) Exam Practice – Question1570

A risk response strategy that can be used for both threats and opportunities is______________


A.
Share
B. Avoid
C. Accept
D. Transfer

Correct Answer: C

Explanation:

Explanation:
Risk exists on every project, and it is unrealistic to think it can be eliminated completely. There are certain risks that simply must be accepted because we cannot control whether or not they will occur (for example, an earthquake). Acceptance is a strategy for
dealing with risk that can be used for both threats and opportunities.