The risk urgency assessment is a tool and technique used for______________


A.
Plan risk responses
B. Identify risks
C. Perform qualitative risk analysis
D. Perform quantitative risk analysis

Correct Answer: C

Explanation:

Explanation:
Risks that may happen in the near-term need urgent attention. The purpose of the risk urgency assessment is to identify those risks that have a high likelihood of happening sooner rather than later. It is combined with the risk ranking to give a final risk severity